As a construction contractor, you know how important it is to have all the necessary information to complete your work on time. Unfortunately, clients are often late in providing construction information.
Late provision of information can lead to the following problems:
- Delayed start and completion of works
- Increased costs
- Client deducting damages for late completion
It is essential to protect yourself and ensure that you are compensated when the client does not provide information by a certain date.
The primary reasons why clients are late with construction information
- Lack of organisation
- Unforeseen circumstances
- Changes in scope
- Limited resources
It is essential that you are protected when these situations arise. I always go through the following steps to protect clients.
Step 1: The first step is to make sure that the contract deals with this issue. The contract should state that the contractor is entitled to be compensated if the client is late issuing construction information. The contractor should have the opportunity to get an extension of time and recover costs.
Step 2: The next step is to list out what the client is responsible for. The client may be responsible for many items:
- Consent from a local authority
- Issue of construction drawings
- Bespoke materials required for the works
- Access to the site
Step 3: Once we have a clear understanding of what the client needs to provide, we can add these items into the contractor’s programme. This serves as a reminder to the client of what they need to do, reducing the chances of a problem in the first place.
Step 4: The contract and the programme now work together. The client is required to provide these items by the dates specified in the programme. This means that the contractor should be able to recover time and costs when the client is late. It is essential that the contractor follows the notice provisions in the contract. A contractor can lose entitlement if they are late issuing notices.
In conclusion, by following these steps, you can protect yourself when the client is late with construction information.
That’s all for today.
See you next week.
Sign up to the newsletter. Every week, you'll get actionable tips to help boost the profits of your construction company.
If you want to increase your profits you need to be able to solve every problem. There are nine basic tools that every contractor needs to make money. In today’s issue, I want to go through the nine tools. Tools 1 to 3 help you manage your tenders. 1. Decision Making Tool- Ensure you price the right opportunities that are going to make money. Every construction contractor needs a way of quickly deciding whether or not to price a tender. You need to make sure you don’t end up with a series of...
If your works have been delayed you may have incurred additional costs. To recover this money, you need to put together a claim for prolongation costs. The first step is to prepare a programme showing the actual or anticipated effect of the events. Then, you can see the extension of time you are entitled to. This will provide protection against damages. The programme also needs to support your claim to recover additional costs. The costs you need to recover can be split between prolonged...
You need to make sure you don’t get hit with delay damages. We were at a weekly progress meeting and the client told us they were going to instruct additional works. They wanted us to install an additional 40 piles. We told them that this would delay completion of our works. For every day that we were late completing out works, the contract stated that the client could deduct damages. This meant that we had to demonstrate that we were entitled to an extension of time. This would protect us...